Milestones

List view

  • The end of the Easter pool test, as well as the fifth bi-weekly development sprint of the merged Perception Team. Review the results gathered during the pool test at the MC-LAB.

    Overdue by 3 year(s)
    Due by April 24, 2022
  • A half sprint for long-running-overdue-tasks.

    Overdue by 3 year(s)
    Due by February 27, 2022
    6/7 issues closed
  • The end of the sixth and last bi-weekly software development sprint of the merged Perception group. The Last Sunday before the exam period. Judgement is upon us.

    Overdue by 3 year(s)
    Due by May 8, 2022
  • The reveal event of the Beluga drone.

    Overdue by 3 year(s)
    Due by April 29, 2022
  • The end of the third bi-weekly development sprint of the merged Perception Team.

    Overdue by 3 year(s)
    Due by April 3, 2022
    6/8 issues closed
  • The end of the second bi-weekly development sprint of the merged Perception Team.

    Overdue by 3 year(s)
    Due by March 20, 2022
    4/6 issues closed
  • The end of the first bi-weekly development sprint of the merged Perception Team.

    Overdue by 3 year(s)
    Due by March 6, 2022
    11/11 issues closed
  • The Factory Acceptance Test before the Easter Pool Test at the MC-LAB.

    Overdue by 3 year(s)
    Due by April 6, 2022
    0/2 issues closed
  • The end of the extraordinary, week-long, fourth software development period for the merged Perception group. This sprint is a week long because of the start with two weeks of testing at the Marine Cybernetics Laboratorium (11.04.22-24.04.22).

    Overdue by 3 year(s)
    Due by April 10, 2022
    0/1 issues closed